The High Court recently handed down its judgment in IGT v The Gambling Commission & Allwyn Entertainment, which concerned the definition of an “economic operator” and in particular, who has standing to pursue a claim against a contracting authority under The Concession Contracts Regulations 2016. The principles established in this case are also likely to apply equally to procurements proceeding via the Public Contracts Regulations 2015.
Following a preliminary hearing, the High Court held that the procurement legislation would only entitle those entities who would be seeking to obtain a public contract with a cause of action to bring a claim (that is bidders or potential bidders).
The case concerned an incumbent provider, Camelot, commencing Court proceedings against the Gambling Commission following the latter’s decision to award a new contract to Allwyn. IGT, Camelot’s sub-contractor, also commenced its own proceedings along similar grounds to those advanced by Camelot.
Following Allwyn purchasing Camelot, Camelot discontinued its claim against Allwyn; however, IGT continued with its claim alone. As a result, the Court had to determine, as a preliminary issue, whether IGT had standing (i.e. the legal right) to bring its challenge as a sub-contractor when it was not the primary bidder.
IGT was unsuccessful on this preliminary issue and the claim was accordingly dismissed. In particular, the Court noted the following:
On the wording of Article 1(3) of the Remedies Directive, an entity who did not seek to obtain the contract (i.e. a bidder) will generally not have the necessary standing to challenge the result of the procurement. That is the straightforward reading of the words…..
As a result of IGT having lost its challenge, it was required to pay some of the Gambling Commission’s costs; however, the situation was not as clear when it came to IGT having to pay Allwyn’s costs.
At a further hearing, the High Court held that the successful bidder, Allwyn, was entitled to recover its costs against IGT on the following basis:
- Allwyn clearly had a separate interest justifying its participation and had participated substantively;
- The value and public importance of the litigation was significant;
- At an early stage, IGT had sought a costs order against Allwyn.
The High Court’s judgment re-affirms previous judgments and has confirmed that an economic operator has to be in it to win it when it comes to pursuing a procurement case against a contracting authority.
Blake Morgan has significant expertise in pursuing and defending contentious procurement matters. If you have any questions regarding this decision on standing to bring a procurement case or procurement law generally, or have any procurement issues, please get in touch with our experts who shall be pleased to help.
Explore more insights
Articles 04 August
Lessons for clients using project bank accounts following a recent insolvency
Project bank accounts, or PBAs, are designed to protect supply chain members by ring-fencing project funds in a…
Articles 29 July
Ten pitfalls local authorities must avoid when implementing the leisure agency model
How can the agency model work for leisure services? We examine the potential pitfalls local authorities must avoid…
Events 09 July
Public Sector Insights Cymru: Health Impact Assessment (Wales) Regulations 2025
We are delighted to invite you to join us for our in-person event: Public Sector Insights Cymru –…

